The contract is option C.
A defect was found during the implementation of the works. The contractor acknowledged the defect and put right the defect at their cost.
This consequently delayed completion of the works. Should the employer be liable to pay for additional preliminaries resulting from this delay?
1 Like
The answer is âit dependsâ, but can be found in option C clause 11.2 (25) which gives the definition of what a Disallowed Cost is. More specifically, the relevant text is in the first two bullet points after âand the cost ofâ.
The first of these states (Disallowed Cost is the cost of) âcorrecting Defects after Completionâ. Given what you have said in that Completion was delayed while it was corrected, this bullet does not apply as it was being corrected before Completion.
The second of these bullets is (Disallowed Cost is the cost of) âcorrecting Defects caused by the Contractor not complying with a constraint on how he is to Provide the Works stated in the Works Informationâ. In non-contractual speak, this means they have not followed a method stated in the technical documentation.
So the answer is
- âYes, they should be paidâ if they followed a method stated in the Works Information and it just turned out to be a Defect (for instance, they laid and compacted concrete properly, but the cubes failed their strength tests). In fact, they should also be reimbursed their direct costs too.
- âNo, it should be disallowedâ for both their direct and indirect/ preliminaries if they failed to follow a method stated in the Works Information.