Should the Contractor submit the proposed contract data for subcontracts to the Project Manager for acceptance?
The Contractor submits the proposed contract data for each subcontract if:
An NEC contract is proposed and
The Project Manager instructs the Contractor to make the submission (see Clause 26.4).