Can a quotation for a Compensation Event be revisited after implementation if the PM subsequently realises that the submitted quotation was unreasonable and a revised quotation should have been instructed?
Can a quotation for a Compensation Event be revisited after implementation if the PM subsequently realises that the submitted quotation was unreasonable and a revised quotation should have been instructed?
@turleya the short answer is no. But it can happen in adjudication.