Programme in Contract Data incorrect

My answer is no, the programme which contained the error has been accepted and is your Accepted Programme. The solution maybe for the Project Manager to instruct you to submit a revised programme detailing what the requirements are or wait until the next submission.

What you can do when creating your CEQ programme is take into account all that has happened since the dividing date, including the error, and see what happens to the critical path / Completion Dates.

Here are some good links which may support your query ?