As the Contractor, we reached Completion of a scheme back in June 23, with a Defects Date of June 24.
Last week, the Client has been asked to carry out further works to the scheme, which they intend to instruct the Contractor to undertake via a PMI.
- Is the Contractor still obliged to carry out these works (they weren’t part of the scope)?
- Is the original contract terms/option still applicable?