@chriscorr, is it possible to reuse (duplicate) the existing proposed instruction workflow from compensation events with a few fields added on the instruction to quote? It already includes instruction to quote, quote, acceptance/non acceptance, requote and SM assessment?
I also do not think we need to consider the impact on compensation events. the task price list is added to the Price List and so are any compensation events. So the ‘contract sum’ is the original total of the Price List, plus the issued Task Orders plus the compensation event.
We do have to consider task order programmes which are in addition to the Contractor’s Plan