A contractor is going to receive a gain share under a Option C contract, as the PWDD is less the total of Prices. In regards to payment and assessment of this, I’m slightly confused, as there seem to be two options (must I comply with both):
54.3 - PM makes assessment on completion regarding forecast of PWDD v Price, then gain is paid in next payment application.
54.4 - PM makes final assessment using final PWDD v Price, final payment.
Therefore must the PM do this process twice and pay them twice? Or is 54.4 just used to make sure it the correct amount was paid in 54.3 after completion?
Thanks All