If an item missing from the Price List but is defined within the Scope, is the Contractor entitled to a CE under 60.1.12?
See clause 20.1, the Contractor is required to “Provide the Works in accordance with the Scope” not in accordance with the Price List, however whether there is CE under clause 60.1(12) will depend on exactly how the Price List was put together. If it is clear that an item is completely missing, as opposed being classed as included in another item then you may have a good case for a CE. 
1 Like