NEC4 ECC: DOES THE CONTRACTOR NEED TO GET PERMISSION OF PM TO PUBLICISE THE WORKS

IF CONTRACTOR WISHES TO PUBLICISE THE WORK I.E. PUBLISH INFORMATION ON THE PROJECT DO THEY NEED THE PROJECT MANAGERS PERMISSION

There is a new clause in NEC4 contracts called “Disclosure” (clause 29 in ECC) that states that they do not disclose information obtained in connection with the works, and that specifically they may not publicise the works without Client’s agreement.