NEC3 Percentage Overheads for SSCC

Can the percentage overheads used for the Shorter Schedule of Cost Components be capped for an Option B contract?

1 Like

When you refer to ā€˜percentage overheadsā€™ are you referring to the percentage additions to the various cost components, such as people overheads, adjustment to Equipment and design overheads, or the fee percentages?

It is possible to amend a contract to achieve most things but as the SSCC under main option B is specifically used in relation to a quotation assessment for a compensation event it is unclear why this would want to be capped.

1 Like