Hi, I wonder if anyone may be able to assist?
I am used to submitting quotations to the project manager upon their instruction under Clause 61.1. For these quotations, i use the shorter schedule of cost components for our submissions.
On the contract I am working on now, i have received a request for quotation for a proposed instruction under clause 61.2. Now the NEC guidance states the SSCC is to be used only for compensation events. As this request is not a CE, any guidance available on the format of the quotation?
Thanks!