I have come across a situation whereby there are multiple delays to the programme and movement of key dates under Contractor Instructions. This has led to multiple compensation events. However, as per Cl 65.3 I do not believe that any fee can be added as none of the CE’s are of the kind referred to in the clause, meaning that the fee cannot be adjusted. The Contractor has included all Key Dates in the Subcontractor Data and there is nothing referenced in the Subcontract Works Information which rules out 60.1.1 as far as I can see and none of the other scenarios are applicable either.
Am i understanding that correctly or is there possibly something I am missing?