Clause 60.1(10) of the ECSC is as follows:
The Contractor is prevented by weather from carrying out all work on the site for periods of time, each at least one full working day, which is in total more than one-seventh of the total number of days between the starting date and the Completion Date. In assessing this event, only the working days which exceed this limit and on which work is prevented by no other cause are taken into account.”
I am assuming that it is always the Completion Date in CD Part 1 that is used in this calculation even if the Completion Date has subsequently changed.
Is this correct?