The Contractor was instructed not to start work on the agreed access date, this instruction was given before the access date, would this be a CE under clause 60.1 (2) or Clause 60.1 (4) of the NEC3 ECC Option A contract?
In this example what is the difference between the two clauses in practice?
1 Like
If you were instructed not to start, presumably by the Project Manager, its 60.1(4). You’ll see that 60.1(2) is about the Client not allowing access, and that’s not what happened.
I would point out that it doesn’t really matter in terms of changes to the Prices or Completion Date; even if it were 60.1(2) I think the delay and therefore the cost is likely to be exactly the same.