On an ECC Option B is it acceptable to include a number of CE’s under one “overarching” CE i.e. one notification/communication.
The PM has included several separate CE’s under one notice.
On an ECC Option B is it acceptable to include a number of CE’s under one “overarching” CE i.e. one notification/communication.
The PM has included several separate CE’s under one notice.
If you are using an online administration tool for managing the flow of NEC communications such as FastDraft then the system will kind of keep the Parties on the right path. Clause 13.7 states any notification has to be communicated separately, and in the electronic system you would need each of these notified separately to trigger the requirements for individual quotations.
So good practice and transparency says yes, and contractually it is probably also a yes. However, a single communication is still probably making it clear that they agree they are compensation events and quotations requested.