Does any minuted items discussed in the meeting change the Works Information or specification ?
No - any such instruction must be communicated separately from other forms of communication to comply with clause 13.7. Any such instruction should be separate and in writing - not lost/buried in minutes of meetings to be a valid form of communication.
No - and industry should be very clear on this - minutes of meetings are not “instructions” or “notifications” under cl. 13. There must be clear compliance with cl 60 process to effect a “change”, and to follow through it to the (bitter) end via - notification - quotation - assessment - implementation. Glenn Hide and I did a White Paper on CEs following the 2016 Built Intelligence NEC People conference, which you might find helpful generally. It can be found on both our websites.
Mine:
Glenn’s: https://gmhplanning.co.uk/?s=how+to+really+