With reference to the last bullet point of clause 60.19
(19) An event; and which ; is not one of the compensation events stated in the contract’.
The guidance notes provide an example of this type of event i.e insolvency of a sub-contractor. However, what about other events that may occur onsite that could potential delay the project. I.e COVID- 19 restriction to the works/Restriction imposed by statue (if X2 is excluded)