How do I have to show a parallel impact on the programme because of two Compensation events?
First Scenario:
CE 1: asbestos found (CE is accepted by employer), with impact on the critical path
CE 2: contaminated water found (CE is accepted by employer), with impact on the critical path but currently in the shadow of CE 1
My understanding:
According to clause 63.3 we have to show the impact on the programme for every compensation event!
This means we have to show the impact on the programme for CE 1 and CE2 separately!
Remark:
It may happen that CEN1 is solved faster. In this case we need the assessed impact of CEN2 on the programme.
Is this approach correct?
Second scenario:
How to show the time-impact on the programme if CE2 affects CE1?
My understanding:
I have to incorporate and to explain the time-impact of CE2 on CE1 on the programme for the CE-assessment of CE1.
Is this approach correct?
With best regards,
Peter (from Germany)