NEC ECC: Can you re-open a closed early warning?

If the Early Warning was closed by the PM but not resolved and there was no new information. Would it be prudent in this scenario to re-open the Early Warning? Or is it always best to raise a new Early Warning in your opinion? Thank you.

1 Like

Technically I don’t think it really matters - but probably cleaner to just notify a new early warning. You can reference the previous raised one within that communication to link it. Presumably the first one was closed for good reason at that stage, and if you now know different or better information it is easier just to notify a new one. Chances are the issue now be subtly different anyway even if related to the new topic.