When assessing the programme impact of a new instruction that includes both a scope increase and reduction, which method should be used (assuming both items are on the critical path):
a) assess the impact of the scope increase and decrease together (i.e partially mitigate each other)
b) assess the impact of the scope increase and decrease separately (i.e increase in terminal float and a delay in completion date)