NEC 4 Option B - Increased Costs

Hi Paul,

Since X1 does not apply, any price increases would only be dealt within the CE mechanism, meaning that, in general, the Defined Cost would be based on current or forecasted costs (e.g. current or forecasted material prices), save for rates set out in Subcontract Data Part 2 for people and Equipment.

Based on the above, your logic is correct. You may wish to check a similar post below: