We are under NEC4 Option C.
The Project Manager notifies the Contractor of a Compensation event and instructs the Contractor to submit a quotation.
The Contractor submits the quotation which includes a certain amount/allowance for Risks.
The quotation is accepted by the PM.
If Risks do not realise, will the Contractor be paid for the Risk allowances made in the quotation?