Misalingment of activity schedule and works information

There is a question and answer which might be relevant to this which I’ve linked below.

My answer is from an NEC3 standpoint, as you’ve not stated this i’m assuming it is. Your position is correct. If the works are described in the Works Information, then the risk for not including the missing scope within the Prices lies with the Contractor.