A bills of quantities states that no certificates will be issued until the contractor has provided a performance bond. After six weeks no performance bond has been produced, but the contractor states that the architect is obliged to certify. Is this corre

In the circumstances stated in the question, the contractor is correct, as established by the case Gilbert Ash (Northern) v Modern Engineering (Bristol).