BI Toolkit
BI Toolkit
ReachBack
Is it a necessity for the final account to be agreed with a contractor before the final certificate is issued?
JCT Contracts
JCT_Experts
5 February 2013 14:58
2
No, this is not a requirement in any of the standard JCT forms.
Related topics
Topic
Replies
Views
Activity
When the final certificate is issued, does it include a definitive amount for workmanship and materials?
JCT Contracts
1
378
5 February 2013
If a final account has been equitably agreed by an accountant and contractor, is it legally permissible for an architect to issue a final certificate equal to the amount agreed?
JCT Contracts
1
449
5 February 2013
After termination, is the contractor entitled to a certificate of practical completion?
JCT Contracts
1
894
6 February 2013
A bills of quantities states that no certificates will be issued until the contractor has provided a performance bond. After six weeks no performance bond has been produced, but the contractor states that the architect is obliged to certify. Is this corre
JCT Contracts
1
343
5 February 2013
What is an architect's legal course of action if a contractor fails to provide final documents within the time period contractually specified, after practical completion has taken place?
JCT Contracts
1
471
5 February 2013