ReachBack
Is it a necessity for the final account to be agreed with a contractor before the final certificate is issued?
JCT Contracts
JCT_Experts
5 February 2013 14:58
2
No, this is not a requirement in any of the standard JCT forms.
Related topics
Topic
Replies
Views
Activity
If a final account has been equitably agreed by an accountant and contractor, is it legally permissible for an architect to issue a final certificate equal to the amount agreed?
JCT Contracts
1
446
5 February 2013
JCT Final Account
General
2
1080
16 January 2023
JCT - Payment Notices for Final Accounts
JCT Contracts
1
1484
22 September 2019
JCT: (Sub contractor) If the main contractor doesn't respond to a final account disputes letter, what is the next step to take?
JCT Contracts
1
500
5 April 2017
When the final certificate is issued, does it include a definitive amount for workmanship and materials?
JCT Contracts
1
376
5 February 2013