Is interest paid if an amount due is corrected in a later certificate following a decision of the Adjudicator or the tribunal?

Is interest paid if an amount due is corrected in a later certificate following a decision of the Adjudicator or the tribunal?

1 Like

Yes. Interest is paid on the difference between the correct amount due and the actual amount due as stated in Clause 51.3.