If an amount due is corrected in a later certificate by the Project Manager in relation to a mistake or a compensation event, when is interest charged from?

If an amount due is corrected in a later certificate by the Project Manager in relation to a mistake or a compensation event, when is interest charged from?

1 Like

Interest is calculated from the date when the increased amount would have been certified if there had been no dispute or mistake until the date when the correcting amount is certified (see Clause 51.3).