If an amount due is corrected in a later certificate following a decision of the Adjudicator or the tribunal, when is interest charged from?
1 Like
Interest is calculated from the date when the increased amount would have been certified had there been no dispute or mistake until the date when the correcting amount is certified (see Clause 51.3).