Is a difference between the original quantities in the Bill of Quantities and the final quantities a compensation event?

There is a difference between the original quantities in the Bill of Quantities and the final quantities in the Bill of Quantities. Is this a compensation event?

A difference between original and final quantities in a Bill of Quantities is not, in itself, a compensation event. However, if the difference delays Completion or the meeting of a Condition stated for a Key Date, it is a compensation event (see Clause 60.5).