How is the Bill of Quantities changed for the whole or a part of a compensation event for work not yet done and for which there is an item on the Bill of Quantities?
For the whole or a part of a compensation event for work not yet done and for which there is an item in the Bill of Quantities, the changes are:
A changed rate,
A changed quantity or
A changed lump sum (see Clause 63.13).