If there is a termination, what does the Project Manager use as the Price Done for Work to Date?

If there is a termination, what does the Project Manager use as the Price Done for Work to Date?

If there is a termination, the Project Manager uses the total of the Defined Cost which the Contractor has paid and which he is committed to pay for work done before termination as the Price for Work Done to Date (see Clause 93.4).