How is the Price for Work Done to Date calculated?

How is the Price for Work Done to Date calculated?

The Price for Work Done to Date is the total of:

	the quantity of the work which the Contractor has completed for each item in the Bill of Quantities multiplied by the rate and

	a proportion of each lump sum which is the proportion of the work covered by the item which the Contractor has completed.