What happens if the final Price for Work Done to Date is greater than the final total of the Prices?

What happens if the final Price for Work Done to Date is greater than the final total of the Prices?

If the final Price for Work Done to Date is greater than the final total of the Prices, the Contractor pays his share of the excess (see Clause 53.2).