ReachBack
If an individual wishes to engage in building work related to foundations, excavations for foundations, any damp-proof course, any concrete or other material to be laid over a site and drains or sewers, how many days’ notice needs to be given to the loca
Planning and Architecture
Part C Site prep
Build_Regs_Advisors
7 February 2013 13:01
2
For any such building work as described in the question, five days’ notice must be given.
Related topics
Topic
Replies
Views
Activity
What two conditions have to be satisfied before building work commences?
General
1
402
7 February 2013
Once a building has been completed, how many days does the occupier / owner have to inform the local authorities of the energy rating of the building?
Part A Structure
1
374
7 February 2013
Before commencing with a legal order to demolish a building, how much notice does the person(s) involved have to give the local authorities?
Part A Structure
1
361
14 February 2013
When is it permissible for building work to begin when an application has been submitted to a local authority?
Part A Structure
1
414
7 February 2013
What is the purpose of a preliminary building site assessment?
Part C Site prep
1
533
15 February 2013