How much should the limit on the Contractor’s total liability under Option X18 be?
1 Like
The limit to the Contractor’s total liability to the Employer should be equal to or higher than the other limiting amounts (Clause X18.1, X18.2, X18.3) to allow for amounts that may become due to the Employer from other rights he may have under the applicable law.