How much is the limit to the Contractor’s liability for damage to the Employer’s property under Option X18?

How much is the limit to the Contractor’s liability for damage to the Employer’s property under Option X18?

1 Like

The limit to the Contractor’s liability for damage to the Employer’s property would usually be an amount within the cover provided by the insurance if the Contractor provides the insurance, or closer the deductible (excess) if the Employer provides the insurance.