Can the Contractor’s liability for indirect or consequential losses be limited under Option X18?

Can the Contractor’s liability for indirect or consequential losses be limited under Option X18?

1 Like

Yes. The Contract Data will state the agreed limit to the Contractor’s liability to the Employer for the Employer’s indirect or consequential loss (see Clause X18.1).