How long does the Contractor have to notify the Project Manager of a compensation event under Option X2?

How long does the Contractor have to notify the Project Manager of a compensation event under Option X2?

The Contractor must notify a compensation event within eight weeks of becoming aware of the event (see Clause 61.3).