How is the ECC structured?
The ECC has four parts:
-
Core Clauses - there are 9 sections of core clauses (General, Contractor’s responsibilities, Time, Testing and Defects, Payment, Compensation Events, Title, Risks and Insurance and Termintation). These clauses should be applicable to any project.
-
Main Option Clauses - there are 6 main option clauses (Option A: Priced contract with activity schedule, B: Priced contract with bill of quantities, C: Target contract with activity schedule, D: Target contract with bill of quantities, E: Cost reimbursable contract, F: Management contract). One of these options is chosen which will determine the pricing mechanism for a particular project.
-
Secondary Option Clauses - there are 18 secondary option clauses (Options X, Y and Z). The user can choose any of these options to fine tune the contract to meet specific needs. However, he doesn’t have to choose any.
-
Dispute Resolution Options - There are two options for this: Option W2 for contracts where the Housing Grants, Construction and Regeneration Act 1996 applies; and Option 1 for when the Act is not applicable.