How is the Bill of Quantities changed for the whole or a part of a compensation event for work already done?

How is the Bill of Quantities changed for the whole or a part of a compensation event for work already done?

For the whole or part of a compensation event for work already done, the change is a new lump sum item (see Clause 63.13).