How is the Bill of Quantities changed for a compensation event for work not yet done and for which there is no item on the Bill of Quantities?

How is the Bill of Quantities changed for the whole or a part of a compensation event for work not yet done and for which there is no item on the Bill of Quantities?

For the whole or a part of a compensation event for work not yet done, and for which there is no item on the Bill of Quantities, the change is a new priced item which is compiled in accordance with the method of measurement (see Clause 63.13).