How is risk apportioned in Option A: Priced Contract with activity schedule?
The Contractor carries all risks other than the Employer’s risks stated in the contract and the financial and time effects of compensation events.
How is risk apportioned in Option A: Priced Contract with activity schedule?
The Contractor carries all risks other than the Employer’s risks stated in the contract and the financial and time effects of compensation events.