Very simple - you assess if you agree that it is indeed a compensation event and that is not caused by the Contractor. Under clause 61.4, if you decide an event has occurred was the Contractors fault or was not a CE then you respond with a decision that the Prices, Completion or a Key Date are not to be changed.
Otherwise they would agree that it is a CE and request a quotation.