How is a change in the law dealt with in Option X2?
A change in the law of the country in which the site is located is a compensation event if it occurs after the Contract Date and if it affects the Contractor’s costs (see Clause X2.1).
How is a change in the law dealt with in Option X2?
A change in the law of the country in which the site is located is a compensation event if it occurs after the Contract Date and if it affects the Contractor’s costs (see Clause X2.1).