How do the Partners act under Option X12?

How do the Partners act under Option X12?

Each Partner works with the other Partners to achieve the Client’s objective stated in the Contract Data and the objectives of every other Partner stated in the Schedule of Partners (see Clause X12.2(1)). Clause X12.3 also states that the Partners are to act in a spirit of mutual trust and co-operation.