Can the PM issue a CE adding more work (changing the works information) after Completion, but before the defects date as per cl61.7?

1 Like

Yes!

Although he would at that point have little control as to how long the Contractor could take (as there is no recourse for over-run as delay damages are redundant after Completion), and the Defect Date would not be changed.

In these type of situations it would be better to have a supplemental agreement agreed between the Parties