Can the period for submitting further information to be considered by the Adjudicator be extended?

Can the period for submitting further information to be considered by the Adjudicator be extended?

Yes. The period for submitting further information to be considered by the Adjudicator can be extended if both Parties agree (see Clause W2.3(2)).