After giving notice of adjudication, how long does a Party have to provide the Adjudicator with information?

After giving a notice of adjudication, how long does a Party have to provide the Adjudicator with the information on which he relies, including any supporting documents?

After giving a notice of adjudication, a Party provides the Adjudicator with the information on which he relies, including any supporting documents, within seven days (see Clause W2.3(2)).