Can the amount of retention be limited?
1 Like
Yes. If the Parties wish to limit the maximum amount of retention, the entry in the Contract Data should be amended by adding ‘with a maximum total amount payable of…’ This figure can be expressed either as a lump sum or as a percentage of the tendered total of the Prices.