Can the Parties limit the total delay damages for the whole of the works?
Yes. If the Parties wish to limit the total delay damages for the whole of the works, the entry in the Contract Data should be amended by adding ‘with a maximum total amount payable of…’. Similar amendments should be made to the Contract Data if it is intended to place a cap on the damages for particular sections of the works where Options X5 and X7 are used together.